Our Mining Experience

The D&L group of companies has been contracted to design and construct various camps in remote locations.

Our experienced teams have proven that they are capable of executing small, medium and  large scale projects within the allocated time and budget all over Australia and also in the Philippines.

RAIL CAMP 95

D&L provided Northern Transportables with skilled tradesman to assist with the construction of a 400man camp for FMG rail in 2019-2020

RAIL CAMP 95

D&L provided Northern Transportables with skilled tradesman to assist with the construction of a 400man camp for FMG rail in 2019-2020

bonnie doon mine camp

BONNIE DOON

D&L and Jakamo Remote Services successfully constructed a 100-man camp for FMG Exploration in 2019

BONNIE DOON

D&L and Jakamo Remote Services successfully constructed a 100-man camp for FMG Exploration in 2019

bonnie doon mine camp

MOUNT GARNET (QLD)

D&L was contracted to construct a 100-man camp at Mount Garnet located in Queensland.

LUZON (PHILIPPINES )

D&L was responsible for the design and construction of a 2000-man camp in the Philippines. 

LUZON (PHILIPPINES )

D&L was responsible for the design and construction of a 2000-man camp in the Philippines. 

YARRIE

D&L carried out rectification works at Yarrie mining camp. Including upgrades to infrastructure and reengineering to meet cyclone rating requirements.

D&L Group have built strong relationships working alongside companies such as BHP, FMG and Gold Road & Gold Fields JV. This has seen us delivering many large mining projects.

BHP

D&L successfully executed a 2-year project in the Pilbara (Newman) working as a preferred contracting company to BHP. D&L utilized our professional team to upgrade the townships aging electrical and HVAC units across 500+ properties, this in turn reduced the average power consumption by 60%.

FMG

D&L were successfully awarded a camp relocation project which was completed in September 2019 and involved the relocation of a 100 & 400 man fly camp in the Pilbara of WA. These works were to allow for the overflow of construction workers from surrounding camps with the new mine site that’s currently under construction

GOLD ROAD & GOLD FEILDS JV

D&L worked with the lead contractor on construction of specific plant rooms at the Gruyere Gold Mine project, providing expert quality building process to detailed specifications.  Our professional trades delivered on time and on budget.  We were capable of adjusting to site conditions and project developments to provide our contractor with variations necessary to get the project phase completed.

BUILDING ON SUCCESS

Email: admin@dlbuildingservices.com

Phone: (08) 6118 0912

Drop us a line

Contact us for anything you want to know! We are happy to answer any question you have as quickly as possible.